Palace of Westminster
Counting from
31 January 2018
This clock starts with the Commons vote to leave the Palace during restoration. It tracks the wait for the wider Restoration and Renewal programme, while maintenance and other repair projects continue.
Awaiting full restoration
The February 2026 proposals recommended a seven-year initial phase capped at £3bn and further development of two long-term options. The NAO’s June 2026 update reported that parliamentary approval was being sought.
Still waiting forDelivery of the Palace’s full Restoration and Renewal programme.
Milestones
- 31 January 2018
MPs vote to move out
The Commons agrees to leave the Palace during restoration works. Source: UK Parliament
- 5 February 2026
Costed proposals published
An initial phase is recommended, with a final decision on the long-term approach proposed by 2030. Source: Restoration and Renewal
- 15 June 2026
The auditor calls for direction
The NAO stresses the need for timely decisions and sustained parliamentary direction. Source: National Audit Office